Required IQ Test for Manufacturing System Category-4

 Required IQ Test for Manufacturing System Category-4 



Required Test Script for Manufacturing Category 4 System

Sr. No.

Test Step

Test Description

Detail Description

1

Test Step-1

Test User Creation for Validation Activities

Create Test Validation  User ID With Assign Privilege for Validation Activity

2

Test Step-2

Verification for Identification of System Under Qualification.

describe identification of the equipment control system and its location. i.e Equipment ID , System ID, Name of Manufacture, System Serial No., Equipment Serial no. and Location etc.

3

Test Step-3

Verification of Master Documents and Vendor Supplied Material

Verified Vendor Supplied Document i.e User Manual, Wiring Diagram, Application and Logic  Program Backup (Backend and Frontend)OS Recovery Tool, Software License Document/CD etc.

4

Test Step-4

Verification of

Hardware Component

Verify Hardware Component Install in Machine

or Equipment, i.e. PLC Processor/ SCAD

Make Model and Serial no. Quantity. Verify All

Electronic Component associate with system

5

Test Step-5

Verifications of Communication Cable

verify the communication cable used for interfacing between system components, i.e PLC SCADA Communication, VFD Communication etc.

6

Test Step-6

Verifications of Power Utilities and Power

circuits Protection

 

verify that the electrical utility has been installed and is available as specified and   protection device installed i.e Utility Power, PLC, IPC Power , UPS Power Supply,  Availability of power circuit protection like MCB/MPCB/Filter

 

7

Test Step-7

System Environment Conditions

verify control system panel area and IPC environmental conditions. like  Record temperature & relative humidity of system area where the PLC and IPC installed.

 

8

Test Step-8

  Verifications of Operating system (OS)

Configuration of PC & Installed Software’s.

 

Verify the OS configuration. (i.e. Processor, RAM, Hard Disk Capacity, Operating System etc).

Verify the installed software packages of IPC with installation path.

 

10

Test-Step-9

General System Inspection for Control Panel

 

Verify for system cleanliness break free wiring, Cleaning, Damage, Name plate, proper cable identification, etc.

11

Test Step-10

Verifications of Available Program Backup for PLC and SCADA

availability of Editable program backup & software of PLC and SCADA With Backup Size, File name, type of Backup media, no. of backup media, backup media Location.

12

Test Step-11

Verification of IP Address

Verify IP Address PLC to IPC and Network IP Address .

13

Test Step-12

Verification of System Domain

Verification System Domain or Not.

14

Test Step-13

Maintenance Calibration Schedule

Verify Maintenance SOP with Verify the Calibration Schedule with Master List and Certificate Associate with the system.